Minister sets February deadline for completion of most road works in Bengaluru
Bengaluru road works sped up, with most projects to finish by February as ministers push for accelerated asphalting and transparency via RIMS dashboard.
At a review meeting, Krishna Byre Gowda said officials must ensure road works were completed within the stipulated time, as complaints about the condition of roads continued to come in from across the city
Updated - November 25, 2026 11:16 pm IST - Bengaluru
With 553 km of roads asphalted so far out of the 2,875 km taken up for development across Greater Bengaluru Authority (GBA) jurisdiction, Greater Bengaluru Development Minister Krishna Byre Gowda on Wednesday directed officials to speed up the remaining works and complete most of them by February.
At a review meeting with officials of the five city corporations, Mr. Gowda said the government had allocated funds for road development and that officials must ensure the works were completed within the stipulated time, as complaints about the condition of roads continued to come in from across the city. “The funds have been provided to address these problems and give people lasting relief. The works must be completed quickly,” he said.
The Minister attributed the slow progress of road works in recent months to the monsoon and the rise in bitumen prices, partly due to the situation in the Middle East. With the rainy season over, he directed officials to increase the pace of asphalting. He also said contractors should be called for discussions and additional workers deployed wherever required.
“The government has also taken up white-topping of 88 roads covering 130 km at an estimated cost of ₹2,321 crore. Work is under way on about 120 km, while another 20 to 25 km is awaiting traffic-related permissions,” Mr. Gowda said, pointing out that the work would be taken up in phases to minimise inconvenience to commuters and that stretches where work could proceed should be completed by December.
The Minister also reviewed the development of stormwater drains, with work taken up on about 200 km. He said surveys were being conducted in coordination with land surveyors, specifically in the city’s peripheral areas, to identify stretches where drains were yet to be developed. The City Corporations had also reclaimed encroached land along drains, including stretches where encroachments covered nearly 20 acres, he mentioned.
Another ₹200 crore has been set aside for buffer roads along stormwater drains. The government plans to develop these roads using Transferable Development Rights (TDR), which, Mr. Gowda said, would add to the road network and improve connectivity.
The Minister further directed officials to bring details of all road projects onto a common dashboard through the Road Infrastructure Management System (RIMS). The information should be updated with live data and made available before the next review meeting, he said.
Published - November 25, 2026 10:10 pm IST
Terms & conditions | Institutional Subscriber
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.