BWSSB has not cleared Ragigudda-Kanakapura elevated corridor, RTI reply reveals
BWSSB states it has not approved or issued NOC for the Ragigudda-Kanakapura elevated corridor, citing lack of feasibility documents and raising concerns over pipeline safety.
Published - November 17, 2026 12:58 am IST - Bengaluru
The RTI application, filed by a Jayanagar resident, had specifically sought details of the project, the feasibility assessment and approvals or NOCs issued by the BWSSB to ensure that its pipelines would not be disturbed by the proposed construction.
The Bengaluru Water Supply and Sewerage Board (BWSSB) has clarified that it has not granted any approval or issued a no-objection certificate (NOC) for the proposed 18.5-km Ragigudda-Kanakapura Road elevated corridor, which is planned along a water pipeline alignment in south Bengaluru. The Board also stated that it does not have the project’s feasibility report or related technical documents on record.
The clarification, issued on October 29 in response to a Right to Information (RTI) application filed on September 18, has only added to the concerns raised by residents opposing the project, who have warned that construction along the alignment could put major Cauvery water pipelines supplying south Bengaluru at risk.
In its reply, the Executive Engineer’s Office said the feasibility report and related technical documents of the proposed elevated corridor were not available in its office. It also categorically stated that the Board had not issued any approval or NOC for construction of any structure along the said route.
The RTI application, filed by a Jayanagar resident, had specifically sought details of the project, the feasibility assessment and approvals or NOCs issued by the BWSSB to ensure that its pipelines would not be disturbed by the proposed construction.
According to a representation submitted by residents under the banner ‘Citizens from South Bengaluru’, four major water mains run along the proposed alignment — three measuring 1,200 mm in diameter and one measuring 1,750 mm. The residents have argued that the pipelines, which are critical to south Bengaluru’s drinking water supply, could be damaged during construction or become difficult to access for regular maintenance once the elevated structure is built.
Citing Section 29 of the Bangalore Water Supply and Sewerage Act, 1964, the residents have argued that construction over the Board’s water mains is prohibited and that the proposed project needs to be examined in light of the statutory restrictions. They have pointed out that the pipelines require regular inspection and maintenance, including access for heavy equipment such as cranes, which could be obstructed by the elevated structure.
The water pipeline issue is among several objections raised by residents against the proposed corridor, which will connect Marenahalli Main Road near Ragigudda Junction to Kanakapura Main Road near the Thalaghattapura NICE Road junction, passing along BWSSB Pipeline Road. The project is being taken up by Bengaluru Smart Infrastructure Limited (B-SMILE) on a toll-based Build-Own-Operate-Transfer (BOOT) model.
Residents have also questioned the need for another elevated road along a stretch already served by the Namma Metro Green Line. They have argued that increasing Metro frequency and strengthening first- and last-mile connectivity would be more effective ways of addressing congestion than adding another road corridor.
Published - November 17, 2026 12:58 am IST
Terms & conditions | Institutional Subscriber
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.