Final trainset for Yellow Line arrives in Bengaluru; sets to boost service frequency

The final trainset for Bengaluru's Yellow Line has arrived, enhancing service frequency and efficiency for commuters.

You don’t have any Active Subscription.

Your active subscription(s)

Account subscription benefits alongside Premium Stories, Editorials, Opinions and more. Unlock these with Subscription

Products you've access to

Additional Subscription Benefits

Need help with your subscription?

Updated - July 27, 2026 05:23 pm IST

A file photo of a trainset for the Yellow Line that was unloaded at Hebbagodi depot in Bengaluru recently. | Photo Credit: SPECIAL ARRANGEMENT

Nearly a year after the inauguration of Bengaluru metro's Yellow Line, the final trainset supplied by Titagarh Rail Systems Ltd. (TRSL) for the corridor arrived in Bengaluru on Monday.

The six-coach train, manufactured by the TRSL at its facility near Kolkata, reached the Hebbagodi depot. According to Bangalore Metro Rail Corporation Limited (BMRCL) officials, the train was unloaded before the installation of couplers and gangways. It will be shifted to the Inspection Bay Line for detailed inspections and testing.

Final trainset for Yellow Line arrives in Bengaluru; sets to boost service frequency

Following the assembly process, the train will undergo static inspections before commencing the mandatory 750-km dynamic testing on the main line.

The officials said that the successful completion of these tests is essential before the trainset can be inducted into commercial passenger service.

The arrival of the 15th and final trainset is expected to improve services on the 19.75-km Yellow Line. At present, 10 trains are operational, enabling metro services at a peak-hour frequency of around seven minutes and every 10 minutes during non-peak hours.

Once all 15 trainsets are commissioned, the BMRCL expects to reduce peak-hour waiting times significantly, with trains operating every four to five minutes. Of the total fleet, 13 trainsets will be deployed for regular passenger services, while two will be maintained as reserve stock to ensure uninterrupted operations during maintenance, emergencies and unforeseen technical issues.

The officials said that the BMRCL aims to make the entire fleet operational by the end of August, subject to the successful completion of testing and certification.

With the completion of the Yellow Line order, the TRSL will now shift its focus to manufacturing and supplying 18 additional trainsets for the Purple and Green Lines under a separate contract.

Published - July 27, 2026 05:22 pm IST

Terms & conditions | Institutional Subscriber

Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.

We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.

Related Stories