Ten of 11 stations on Kochi metro’s Pink Line to have entry/exit from both sides of road
Kochi metro’s Pink Line will feature dual-sided entry/exit at 10 stations, with Smart City terminal limited to right-side access, as works accelerate toward 2027 completion.
Terminal station at Smart City to have entry/exit only on the right hand side; foot overbridge mulled for members of the public to access the station
Updated - November 08, 2026 01:26 am IST - KOCHI
Work in progress for the Kochi metro’s Palarivattom Junction station. It will be the first station on the Pink Line. | Photo Credit: John L. Paul
With about 70% of the viaduct of the Kochi metro’s 11.20-km Kakkanad extension (Pink Line) complete and the laying of tracks set to begin, pending works on all 11 stations in the corridor are set to gather momentum after an initial lull. This is in keeping with the revised deadline of August 2027, which has been set to complete the works on the extension, official sources said.
Contrary to the perception that a few stations will have entry/exit only from one side of the road, 10 of the 11 stations will have entry/exit from both sides of the road beneath the upcoming metro extension. The terminal station, whose work is set to begin on the Smart City premises, will have entry/exit only on the right hand side, while a foot overbridge will provide a link for members of the public to access the station, they added.
The structural work on the entry/exit of the Chittetukara station is over on both the left hand side and the right hand side of the road, while that of the left-hand side of the KINFRA Park station is over. Work on the right hand side of the Vazhakkala station is over, and architectural work has begun. Structural works on the left hand side entry/exit of the stations at Civil Station Junction and Cochin SEZ are scheduled to be completed by the first week of December.
The foundation works of the entry/exit of the Chembumukku station whose land acquisition suffered delay is over, and rest of the works is set to gather pace on both sides of the road, it is learnt.
Metro sources attributed the delay in commencing work on the right hand side entry/exit of Palarivattom Junction and Padamugal stations to hassles associated with land acquisition. The requisite plots of land for the two stations will be acquired by the end of December. The pending works on most metro stations will gather pace in the coming weeks, since the requisite pre-fabricated structures are ready at the casting yard. They will be transported in lorries and launched at the stations concerned. This will be followed by architectural works, laying of tracks, and installation of signals and telecommunication equipment, lifts and escalators, to name a few.
The first station on the Pink Line is at Palarivattom Junction, followed by stations at Alinchuvadu, Chembumukku, Vazhakkala, Padamugal, Civil Station Junction, Cochin SEZ, Chittettukara, KINFRA Park, Infopark, and Smart City.
Published - November 07, 2026 08:26 pm IST
Terms & conditions | Institutional Subscriber
Comments have to be in English, and in full sentences. They cannot be abusive or personal. Please abide by our community guidelines for posting your comments.
We have migrated to a new commenting platform. If you are already a registered user of The Hindu and logged in, you may continue to engage with our articles. If you do not have an account please register and login to post comments. Users can access their older comments by logging into their accounts on Vuukle.